Public Contracts - Options when responding to COVID-19

Together we are Forbes

Governance, Procurement & Information Article

26 March, 2020

Gemma_Duxbury
Gemma Duxbury
Partner

In these current exceptional circumstances, you may need to procure goods, services and works urgently. As you are probably already aware, authorities are permitted to do this using regulation 32(2)(c) under the Public Contract Regulations 2015.

So, what can you do?

Option 1 - Direct award due to extreme urgency

Regulation 32(2) sets out the following:

The negotiated procedure without prior publication may be used for public works contracts, public supply contracts and public service contracts in any of the following cases: ...

(c) insofar as is strictly necessary where, for reasons of extreme urgency brought about by events unforeseeable by the contracting authority, the time limits for the open or restricted procedures or competitive procedures with negotiation cannot be complied with.

… the circumstances invoked to justify extreme urgency must not in any event be attributable to the contracting authority.

Therefore, you may, in responding to the outbreak of COVID-19, enter into contracts without competing or advertising, so long as you are able to demonstrate the following tests have all been met:

  1. There are genuine reasons for the extreme urgency, eg:
  • you need to respond to the COVID-19 consequences immediately because of public health risks, loss of existing provision at short notice, etc;
  • you are reacting to a current situation that is a genuine emergency - not planning for one.

2. The events that have led to the need for extreme urgency were unforeseeable, eg:

  • the COVID-19 situation is so unusual that the consequences are not something you should have predicted.

3. It is impossible to comply with the usual timescales in the PCRs, eg:

  • there is no time to run an accelerated procurement under the open or restricted procedures or competitive procedures with negotiation;
  • there is no time to place a call off contract under an existing commercial agreement such as a framework or dynamic purchasing system.

4. The situation is not attributable to the contracting authority, eg:

  • you have not done anything to cause or contribute to the need for extreme urgency.

You MUST:-

  1. keep a written justification that shows the satisfaction of these tests.
  2. You should carry out a separate assessment of the tests before undertaking any subsequent or additional procurement to ensure that they are all still met, particularly to ensure that the events are still unforeseeable. For example, as time goes on, what might amount to unforeseeable now, may not do so in future.
  3. limit your requirements to only what is absolutely necessary both in terms of what you are procuring and the length of contract.

Delaying or failing to do something in time does NOT make a situation qualify as extremely urgent, unforeseeable or not attributable to the contracting authority. This is because:

  • the PCRs expect a contracting authority to plan its time efficiently so that it is able to use a competitive procedure;
  • competitive alternatives (eg. an accelerated open procedure) can be completed quickly;
  • case law has held that knowing that something needs to be done means it is foreseeable;
  • a contracting authority's delay or failure to do something is likely to mean that the situation is attributable to the contracting authority.

It is important that you continue to achieve value for money and use good commercial judgement during any direct award. Whilst prices may be higher than would be expected in a regular market, any abnormally high pricing should be approved by the appropriate financial officer.

Additionally, you are encouraged to consider contractual mechanisms to ensure that you have the ability to secure pricing reductions through the life of the contract. Where this is not possible, it is recommended a log should be kept and reasoning provided for future auditing.

Option 2 - Direct award due to absence of competition or protection of exclusive rights

Regulation 32(2) of the PCRs also sets out that the negotiated procedure without prior publication may be used:

(b) where the works, supplies or services can be supplied only by a particular economic operator for any of the following reasons: ...

(i) competition is absent for technical reasons,
(ii) the protection of exclusive rights, including intellectual property rights,

… but only where no reasonable alternative or substitute exists and the absence of competition is not the result of an artificial narrowing down of the parameters of the procurement.

You may make a direct award where the works, goods or services needed to respond to COVID-19 can ONLY be supplied by a particular supplier because:

  • competition is absent for technical reasons eg there is only one supplier with the expertise to do the work, produce the product or with capacity to complete on the scale required; or
  • the protection of exclusive rights, including intellectual property rights eg:

(i) the supplier owns those rights (including intellectual property rights);
(ii) it has the exclusive right to exploit intellectual property rights.

BUT this is only when:

  • there is no reasonable alternative or substitute available; and
  • you are not doing something which artificially narrows down the scope of the procurement eg by over-specifying the requirement.

You must:

  1. keep a written justification that satisfies these tests
  2. carry out a separate assessment of the tests before undertaking any repeat procurement to ensure these tests have been met.

Option 3 - call off from an existing framework or dynamic purchasing system

Central purchasing bodies, such as the Crown Commercial Service, offer public bodies access to a range of commercial agreements including framework agreements and dynamic purchasing systems (DPS).

It is possible to use one of these commercial agreements as long as:

  • you were clearly identified as a permitted customer in the original OJEU notice or the invitation to confirm interest;
  • the goods, services or works to be procured fall within the scope of those covered by the contract, framework agreement or DPS;
  • the contract, framework agreement or DPS was procured in accordance with the PCRs;
  • the terms of the contract, framework agreement or DPS are suitable and meet your requirements without the need for significant changes.

A framework agreement will provide for direct awards, mini-competitions or both.

You MUST:

  1. follow the procedure for awarding a call off contract set out in the framework agreement. An award under a DPS has to be by mini-competition and the minimum time for receipt of tenders is 10 days.

Option 4 - call for competition using a standard procedure with accelerated timescales

You can reduce the minimum timescales for the open procedure, the restricted procedure and the competitive procedure with negotiation if a state of urgency renders the standard timescales impracticable. The minimum time limits vary (see regulations 27(5), 28(10) and 29(10) respectively). For procurements under the open procedure, timescales can be reduced to 15 days for receipt of tenders plus the minimum 10 days for the standstill period.

There is no express requirement for the situation to be unforeseeable or not attributable to the contracting authority but you should set out in your OJEU notice a clear justification eg:

"The COVID-19 outbreak has given rise to an urgent need for the supply of [description of what is being procured] because [explanation of urgency]. This does not give [name of contracting authority] sufficient time to comply with the standard [open procedure / restricted procedure / competitive procedure with negotiation] timescales for this procurement. [Contracting authority] considers this to be a state of urgency which it has duly substantiated. Accordingly, [contracting authority] is using the accelerated time limits permitted under the Public Contract Regulations 2015 (regulation [27(5) for the open procedure / 28(10) for the restricted procedure / 29(10) for the competitive procedure with negotiation]) in respect of this procurement".

Contracting Authorities can also consider the use of the Light Touch Regime for specific health and social care related services (see regulation 74-77). While contracting authorities are required to advertise contracts in OJEU and publish contract award notices, you are free to use any process or procedure you choose to run and are not required to use the standard procurement procedures (open, restricted etc). You are also free to set your own timescales as long as they are reasonable and proportionate.

Option 5 - extending or modifying a contract during its term

Regulation 72(1) sets out the following:

Contracts … may be modified without a new procurement procedure … in any of the following cases:

(c) where all of the following conditions are fulfilled:

(i) the need for modification has been brought about by circumstances which a diligent contracting authority could not have foreseen;
(ii) the modification does not alter the overall nature of the contract;
(iii) any increase in price does not exceed 50% of the value of the original contract or framework agreement.

YOU MUST:

  1. keep a written justification that satisfies these conditions, including limiting any extension or other modification to what is absolutely necessary to address the unforeseeable circumstance. This justification should demonstrate that your decision to extend or modify the particular contract(s) was related to the COVID-19 outbreak with reference to specific facts, eg your staff are diverted by procuring urgent requirements to deal with COVID-19 consequences, or your staff are off sick so they cannot complete a new procurement exercise. You should publish the modification by way of an OJEU notice to say you have relied on regulation 72((c).

Multiple modifications are permissible, however each one should not exceed the 50% of the original contract value. You should also consider limiting the duration and/or scope of the modification and running a procurement for longer-term/wider scope requirements alongside it.

There are other grounds available under regulation 72 for extending contracts, including: if the proposed variation has been specifically provided for in the contract (regulation 72(1)(a)); where a change of contractor cannot be made for economic or technical reasons (regulation 72(1)(b)), and where the modifications are not substantial (regulation 72(1)(e))

If more than one ground is applicable this may lower the legal risk and therefore you should ensure all relevant grounds are included in your written justification.

Other thoughts…

Moving forward you may need to take action in response to supplier claims of 'force majeure' or contract 'frustration'. These and other issues will be covered in future PPNs and updates from Forbes.

Depending on the specific nature of your requirement there may be further options under the PCRs, such as the additional delivery of supplies from an existing supplier (regulation 32(5)), additional similar works or services from an existing supplier (regulation 32(9)), or using the services of a subsidiary of another contracting authority (regulation 12). These are not covered in the latest guidance and do have their own specific requirements.

You should ensure you keep proper records of decisions and actions on individual contracts, as this could mitigate against the risk of a successful legal challenge. If you make a direct award, you should publish a contract award notice (regulation 50) within 30 days of awarding the contract.

For more information contact Gemma Duxbury in our Governance, Procurement & Information department via email or phone on 0333 207 4239. Alternatively send any question through to Forbes Solicitors via our online Contact Form.

Learn more about our Governance, Procurement & Information department here

Coronavirus: Managing your Contracts and Costs

COVID-19: Sharing Tenant Personal Information

Contact Us

Get in touch to see how our experts could help you.